Title and Location BRINE PROCESS SECONDARY CONTAINMENT,
Chemical Processing Facility, Maine
Project Description Multi-phase project to relocate process equipment and piping within a concrete containment structure.  Components include FRP tanks and piping and titanium pumps and equipment for 1500 gpm, 180 degree F brine stream, plus precoat and sludge systems.
My Role and Accomplishments of Note Lead Mechanical Engineer
Employer   Enterprise Engineering, Inc.
     
Title and Location UNIT 5 DISTRICT HEAT STEAM TIE LINE
Power Plant, Alaska
Project Description Provision of 260' of 12" steam piping for cogeneration plant low pressure steam re-route.
My Role and Accomplishments of Note Assisting Mechanical Engineer:  Performed piping flexibility/restraint analysis using CAESAR-II software program.
Employer
  Enterprise Engineering, Inc.
TOP

   
Title and Location   RELOCATE COOLING PUMPS
Department of Defense Facility, Maine
Project Description

Relocate vertical turbine pumps into new building and repair concrete pier. Pumps transfer sea water for cooling large electical equipment.

My Role and Accomplishments of Note Design Manager and Mechanical Engineer for latter half of project.  Helped re-focus and complete a project which had languished for some time.
Const. Cost $590,000
Employer   Enterprise Engineering, Inc.
TOP
 
 
Title and Location WAX HANDLING SYSTEM 
Candle Maker, Maine
Project Description Provision of stainless steel piping system for receiving wax from tanker trucks, storing the wax in two 10,500 gallon tanks and transferring wax to the candle production line.  Tanks and piping were heated to maintain flowability of wax.
My Role and Accomplishments of Note Lead Mechanical Engineer
Const. Cost $200,000
Employer   Enterprise Engineering, Inc.
TOP
   
 
Title and Location DESUPERHEATING PIPING MODIFICATIONS 
Paper Mill, Maine
Project Description Fast-track study and upgrade of desuperheater water supply control system at industrial cogeneration plant.  Lack of documentation necessitated thorough investigation of numerous water destinations.
My Role and Accomplishments of Note Lead Mechanical Engineer.
Const. Cost $50,000
Employer   Enterprise Engineering, Inc.
TOP
   
 
Title/Location STEAM LINE REPLACEMENT
Paper Mill, Maine
Project Description Design analysis, using Triflex computer program, of new 12" diameter superheated steam line, steam conditioning valve and 20" diameter 160 psig header.
My Role and Accomplishments of Note Lead Mechanical Engineer.
Const. Cost $300,000
Employer   Enterprise Engineering, Inc.
TOP
   
 
Title and Location BLOW LINE REPLACEMENT
Paper Mill, Maine
Project Description Developed installation drawings, as subcontractor to the piping vendor, for replacement of a portion of two 18" lines for pneumatic conveyance of tree bark and rubber tire chips.
My Role and Accomplishments of Note Lead Mechanical Engineer:  Received compliments for accuracy of work from the mill and the installation contractor.
Const. Cost $600,000
Employer   Enterprise Engineering, Inc.
TOP
   
 
Title and Location ACID TANK RELOCATION
Paper Mill, Maine
Project Description Study and design of new sulfuric acid storage and dispensing system for mill wastewater treatment facility.  Included new instrumentation and controls for pH control of wastewater.
My Role and Accomplishments of Note Lead Mechanical Engineer.
Const. Cost $250,000
Employer   Enterprise Engineering, Inc.
TOP
   
 
Title and Location SOLVENT ADDITION SYSTEM FOR BLDGS 1019, 1020, 1024 & 1026
Department of Defense Facility, Maryland
Project Description System for storage and automatic metering of solvents, plasticizers and nitro-esters to two propellant mixing machines.  Incorporated Underground Storage Tanks, PLC-based control system, plasticizer heating system and batch weighing system.
My Role and Accomplishments of Note Project Manager and Lead Mechanical Engineer until I left firm to move to Maine.
Const. Cost $720,000
Employer   Clark-Smith Associates
TOP

 
   
 
Title and Location UPGRADE BLDG 1649 FOR HOPPER CLEANING 
Department of Defense Facility, Maryland
Project Description Provision of systems for rinsing and drying solid propellant hoppers. Also provided system for recycling rinse water.  Utilities included provision of approximately one mile of exterior steam and compressed air piping.
My Role and Accomplishments of Note Project Manager / Lead Mechanical Engineer
Const. Cost $288,000
Employer   Clark-Smith Associates
TOP
   
 
Title and Location COMPRESSED AIR DRIER BOOSTER HEATERS 
Department of Defense Faciltiy, Virginia
Project Description Provision of 75 kW electric heaters and electronic control systems on three existing desiccant-type air dryers for shipyard air distribution system.
My Role and Accomplishments of Note Project Manager / Lead Mechanical Engineer
Const. Cost $47,000
Employer   Clark-Smith Associates
TOP
   
 
Title and Location REPLACE QUENCH TANKS 
Department of Defense Facility, Virginia
Project Description Provision of quench system consisting of oil tank, jacketed water tank, oil pump and piping (all in a secondary containment structure) for a metallurgical heat treatment process.
My Role and Accomplishments of Note Project Manager / Lead Mechanical Engineer
Const. Cost $150,000
Employer   Clark-Smith Associates
TOP
   
 
Title and Location MISCELLANEOUS MODIFICATIONS AND INSTALLATIONS TO OPERATING BUILDINGS 
Department of Defense Facility, Maryland
Project Description Work included 1) HVAC for a munitions testing lab, 2) safety upgrades to a rocket test bay door, 3) compressed air drier for process controls, 4) temperature/humidity control system for propellant milling process and 5) propellant mixing bay ventilation.
My Role and Accomplishments of Note Project Manager / Lead Mechanical Engineer
Const. Cost $255,000
Employer   Clark-Smith Associates
TOP
   
 
Title and Location MODIFICATIONS TO PNC FACILITY
Department of Defense Facility, Maryland
Project Description Performed energy conservation study on existing process at Plastisol Nitrocellulose pilot plant.  Also provided wastewater treatment system, local/general ventilation systems and heat trace of heptane piping.
My Role and Accomplishments of Note Project Manager / Lead Mechanical Engineer
Const. Cost $337,000
Employer   Clark-Smith Associates
TOP
   
 
Title and Location VARIOUS MECHANICAL PROJECTS
Department of Defense Facility, Virginia
Project Description Work included provision of 1) HVAC for office space, 2) underground steam lines, 3) jockey pump for base salt water system and 4) heating system for low-level nuclear waste storage building.
My Role and Accomplishments of Note Project Manager / Lead Mechanical Engineer
Const. Cost $175,000
Employer   Clark-Smith Associates
TOP
   
 
Title and Location PROCESS ENERGY CONSERVATION STUDIES 
Soybean Processing Facility, Virginia
Project Description Investigated economics of replacing electric motors with steam turbines on various equipment and optimized steam usage of degumming process.
My Role and Accomplishments of Note Lead Mechanical Engineer
 
Employer   Clark-Smith Associates
TOP
   
 
Title and Location REPAIR POWER HOUSE, BLDG 873
Department of Defense Facility, Maryland
Project Description Provision of two steam conditioning valves in an existing steam cogeneration plant.
My Role and Accomplishments of Note Project Manager / Lead Mechanical Engineer
Const. Cost $200,000
Employer   Clark-Smith Associates
TOP
   
 
Title and Location REPLACE HEATING CONTROL SYSTEM, BLDGS 727, 728, 729 & 731
Department of Defense Facility, Maryland
Project Description Provision of PLC-based control systems and connections to existing pneumatic systems for controlling propellant curing processes.  Included central micro-computer and overhead communication cable for remote monitoring and programming of controllers.
My Role and Accomplishments of Note Project Manager and Lead Instrumentation Engineer.  I developed a performance/design specification for the systems which procured the installation/interconnection of owner furnished PLC's at a competitive price.
Const. Cost $120,000
Employer   Clark-Smith Associates
TOP
   
 
Title and Location REPAIR ASH GRATE AND HOPPER SYSTEMS, BLDG Z-309
Department of Defense Facility, Virginia
Project Description Provision of hydraulic drive systems and controls for moving ash grates in refuse-burning steam plant.
My Role and Accomplishments of Note Lead Mechanical Engineer
Const. Cost $83,000
Employer   Clark-Smith Associates
TOP
   
 
 

 

 

 

 

 

 

 

 

 

 

 

 

 







The photos above show the two 18" pneumatic conveying pipelines installed by